Q. A can complete a task alone in 8 days, while B takes 12 days to do it by herself. Together with C it takes them 4 days to complete the work. If C and D together can complete the task in 15 days, then how many days will D need to complete the task by herself?

A) 32

B) 36

C) 30

D) 40

✔ Correct Answer: 40