Q. If 20 men working 8 hours per day can complete a piece of work in 21 days. How many hours per day must 48 men work to complete the same job in 7 days?
A) 20
B) 12
C) 15
D) 10
✔ Correct Answer: 10
Exam Insight
-
A) 20
B) 12
C) 15
D) 10
✔ Correct Answer: 10
-